Design and build4 min read

Reading a contractor’s build-up

Measured items, provisional allowances and exclusions. Where a build-up tells the truth and where it starts disputes.

A finished open-plan kitchen with marble countertop, grey cabinetry and a wine fridge, showing the quality finish that justifies a detailed cost breakdown.
A finished open-plan kitchen with marble countertop, grey cabinetry and a wine fridge, showing the quality finish that justifies a detailed cost breakdown.Case study

Design and build company in London. Designers, a quantity surveyor and builders, under one contract.

A contractor sends you a build-up. Twenty pages of items, each with a rate and a sum.

It is not a render. It is not an artist’s impression.

It is a claim. Every line says what the job will cost and why.

Reading it line by line is the cheapest way to catch mistakes early.

Early catches save time and money.

What a build-up is, and why it matters

A build-up lists every measured item and every cost assumption.

It lists every exclusion too.

It is the contractor’s answer to one question: where does this price come from?

An honest build-up shows which costs are pinned down.

It shows which costs sit on assumptions.

A poor build-up hides assumptions under Provisional Allowance.

It leaves you guessing at the total.

Your job is to decide which is which before you agree the number.

A luxury kitchen mid-renovation showing MEP first-fix work, with marked-up walls and exposed services before decoration
First-fix stage where MEP coordination matters. Every service route and size affects cost.Work in progress

Measured items: the costs that are pinned

A measured item comes from the drawings.

It is priced using a schedule of rates.

Example: kitchen units 2.4 metres, labour 16 hours.

That line is as honest as the drawing.

If the drawing is accurate, the item is accurate.

If the drawing is wrong, the item fails.

Before accepting any measured item, check the source drawing.

The drawing must be current and complete.

Provisional allowances: where the guess sits

A provisional allowance means the contractor does not know the exact cost.

It says: I cannot measure this, so I am estimating.

Every provisional allowance is a risk.

The real cost may be more or less.

Common examples: party wall, structural engineering, archaeological finds.

Also asbestos removal and other specialist trades needing a site visit.

A good build-up tells you which allowances sit in which sections.

A poor one lumps them all under contingency.

Then you are left guessing.

Exclusions: what is not in the number

An exclusion is something the client or architect handles.

Another contract may handle it too.

Client to supply: kitchen appliances.

Architect to arrange: party wall.

These are not the contractor’s cost.

But they are your costs.

A good build-up lists exclusions clearly.

Nothing gets missed and nobody claims it twice.

Unwritten exclusions will be argued about later.

Overheads and profit: the numbers under the detail

Once all measured items are listed, the contractor adds overheads.

Then profit is added.

Overheads are the cost of running the site.

Also the cost of running the office and the machinery.

Profit is the contractor’s return for carrying risk.

These are legitimate costs.

But they are also where bad estimating hides.

If a detailed item is too low, the shortfall absorbs here.

It is not carried on the job.

If overheads look unusually low or high, question them.

A site showing MEP first-fix work with electrical conduit, plumbing routes and mechanical services marked on walls before final decoration
First-fix showing MEP routes and coordination. Services costs are measured items, not allowances.Work in progress

Red flags to watch for

A build-up with no provisional allowances is not truthful.

Every project has unknowns.

One-line items covering whole categories (kitchen, bathrooms, services). Cost certainty comes from clarity, which means every cost is stated.

Exclusions that are vague or missing.

If you have to ask what is in, that is a problem.

Provisional allowances without notes.

You need to know what they cover and why.

How to use a build-up to manage the job

A good build-up does more than price the job.

It is your map of what will happen.

It shows the order things happen in too.

If a measured item differs on site, you can see the cost.

Then you can argue it fairly.

If a provisional allowance comes in lighter, that is a saving.

If it comes in heavier, you know where cost went.

Then you can decide to absorb it or challenge it.

That is the difference between understanding a job.

Or being surprised by what happens at completion.

Starting from facts, not from wishes

A good build-up tells you where the numbers come from.

It shows you measured items and provisional allowances.

It tells you the rates the contractor is working from.

If the total looks high, you can see why.

If it looks low, you can spot where it is thin.

The build-up is your roadmap to understanding cost.

Without it, the price is just a number.

With it, you know what you are agreeing to.

Why NU build-ups are open-book

We price every project open-book.

That means measured items from the drawings.

Provisional allowances are named and sized.

Exclusions are listed.

You see the rates and the costs and the total.

Everyone sees it before anyone signs anything.

This is not generous. It is practical.

A job priced fairly at the start stays fairly priced to the end.

Need a build-up you can actually read and understand?Fill out the contact form or call 020 7731 6841 and let’s walk through a live project together.

This is the work we do. Design and build company in London, or ask for a cost estimate.

Published 17 November 2026. Written by the NU Projects studio, edited since for house style and accuracy.

Filed underDesign and build

Your home

Reading about it is one thing. Building it is another.

Your name and one way to reply are enough. It goes straight to the studio.

A phone number or an email is enough. We only need one.

Where did you find us? Optional
Optional, it helps us prepare
What is the work?