In short.
The Portman estate covers 110 acres of Marylebone. Alterations usually need a licence to alter, and leases vary widely. Consent takes effect once the licence completes. Weekend work is not allowed on the estate.
Planning authority: Westminster City Council.
This guide summarises published documents, read on 19 November 2026. Your lease decides. Check the current documents before you apply.
Who gives consent.
The estate covers 68 streets, 650 buildings and four garden squares.
Your lease comes first. Some leases ban alterations outright.
You may need your immediate landlord’s approval as well as the freeholder’s.
Sub-tenants apply through the head lessee or residents’ company.
Portman usually appoints a consultant to manage each application.
Three forms of consent.
- An approval letter, for simpler works
- An approval letter with an in-house licence
- A formal licence to alter drawn by Portman’s solicitor, for larger projects
Each comes with technical schedules and approved drawings.
What Portman asks to see.
- The application form, a description and photographs
- Existing and proposed drawings, sections and elevations at 1:100 or larger
- Structural and M&E drawings and calculations
- Planning and listed building consent, applied for or granted
- The Building Control application or approval
- The cost of works to a builder’s finish
- Later: programme, method statements, asbestos survey and party wall notices
Fees, deposit and insurance.
- An application fee, paid before the estate starts work on it
- A solicitor’s undertaking for legal, surveying and monitoring costs
- A deposit that could be £10,000 or more, refunded after sign-off
- Public and employers’ liability cover of at least £10 million each
- A premium, where an absolute covenant must be varied
Timescales.
An approval letter normally follows within four weeks of a valid application.
Complex schemes take longer. Targets are set at the first inspection.
Technical rules.
- Hoardings painted to match the masonry or stucco
- No boiler flues on principal elevations
- Cast-iron external pipework, and no plastic push-fit pipes
- Wet underfloor heating is not looked on favourably
- Hard floors only with acoustic insulation, and bedrooms carpeted
- Wet areas tanked, with leak detection
Working hours.
- Weekdays 8am to 6pm
- No weekend or bank holiday work
- Further limits on noisy work may be added
That is stricter than Westminster, which allows Saturday mornings.
Basements.
Portman’s guide sets no basement policy of its own.
Westminster’s City Plan Policy 50 applies.
It allows one storey under no more than half the garden.
A listed home’s basement must not unbalance its original hierarchy of rooms.
The order of consents.
- 01
Read your lease. Find any head lessor or residents’ company, whose consent comes first.
- 02
Talk to the estate early, before drawings are fixed.
- 03
Apply for planning permission and listed building consent from the council.
- 04
Serve party wall notices: two months for party walls, one month for excavation.
- 05
Get Building Regulations approval from the council or an approved inspector.
- 06
Meet the estate’s conditions, complete the licence, then start on site.
How we help.
NU Projects designs, prices and builds prime London homes under one contract.
We prepare the drawings, structural details and method statements an estate asks for.
We run planning, listed building consent, party wall and building control alongside.
What homeowners ask.
How long does a Portman licence to alter take?
An approval letter is normally issued within four weeks of a valid application. Larger schemes with a solicitor’s licence take longer.
Is there a deposit for works on the Portman estate?
There may be. Portman says it could be £10,000 or more. It is refunded within a month of sign-off.
Can builders work on Saturdays on the Portman estate?
No. Portman allows work from 8am to 6pm on weekdays only. Weekends and bank holidays are closed.
When can work start on the Portman estate?
Once the estate’s conditions are met and fees paid. With a solicitor’s licence, consent only takes effect once the licence completes.
Sources.
Each source was read on 19 November 2026.
- Portman, licence to alter: residential tenant guide, 2024
- Portman, licence to alter questions, 2026
- Portman, licence to alter documents, 2026
- Westminster City Plan, Policy 50 basements, 21 January 2026
- Westminster Code of Construction Practice, May 2026